Data centres

Data centre infrastructure: power, cooling, fire and controls.

We deliver the data centre infrastructure below the server: MV/LV distribution, UPS and generators, chilled-water and CRAH cooling, clean-agent fire suppression, BMS, EPMS and DCIM integration, and integrated systems testing.

A rendering of a 4 MW data centre, assembled layer by layer from the site slab to the live facility

The build, on scroll

Seven layers, in the order they go up.

A rendering of a 4 MW data centre, assembled layer by layer from the site slab to the live facility
  1. Layer01 / 07

    Site and civil

    What it is
    A plot shaped for heavy plant, heat, and dust.
    What we supply
    Plant pads, duct banks, drainage, earthing, and the fenced yard.
    The standard it meets
    TIA-942 site requirements, Rated-3
  2. Layer02 / 07

    Structure and envelope

    What it is
    A steel frame and an insulated shell, with a hall inside it.
    What we supply
    The portal frame, insulated shell, and two-hour rated partitions.
    The standard it meets
    SBC 801 compartmentation, two-hour rated
  3. Layer03 / 07

    Electrical

    What it is
    Two paths from the grid to every rack, with the engine behind both.
    What we supply
    MV intake, transformers, LV boards, UPS, generators, and busway.
    The standard it meets
    Uptime Tier III, EN 50600 power classes
  4. Layer04 / 07

    Cooling

    What it is
    Rejecting four megawatts of heat into a fifty-degree afternoon.
    What we supply
    Chiller plant, pumps, buffer tank, CRAH units, and containment.
    The standard it meets
    ASHRAE TC 9.9, A1 envelope
  5. Layer05 / 07

    Fire, safety and security

    What it is
    Detection measured in seconds, suppression that leaves no residue.
    What we supply
    Detection, clean-agent suppression, access control, and CCTV.
    The standard it meets
    NFPA 75 and 2001, SBC 801
  6. Layer06 / 07

    IT fit-out

    What it is
    Four hundred racks, sixteen rows, every one fed twice.
    What we supply
    Containment, cable tray, fibre routes, and the meet-me room.
    The standard it meets
    TIA-942 and BICSI 002
  7. Layer07 / 07

    Controls and commissioning

    What it is
    Everything measured, everything tested, then handed over.
    What we supply
    BMS, EPMS, and DCIM, and the integrated systems test.
    The standard it meets
    Uptime Tier III Certification support
Our scope

Everything below the server is ours.

Our scope is everything below the server: the two paths from the grid to every rack, the plant that rejects megawatts of heat into a Gulf summer, the clean-agent fire system, the controls that watch all of it, and the commissioning that proves it. The compute, storage, and network inside the racks belong to the operator; the facility they depend on is ours.

  • Green Square: power, cooling, fire, controls and structure
  • The operator: compute, storage and network
The same rendering, with the operator's racks in grey and Green Square's infrastructure in colour
Power and cooling

Two chains carry the load: power in, heat out.

Power path: two paths from the grid to every rack

  1. Utility intake

    Dual 13.8 kV intakes from the Saudi Electricity Company

  2. MV switchgear

    Metal-clad switchgear, two sections and a bus tie

  3. Transformers

    N+1 cast-resin units, derated for 50 °C

  4. Generators

    N+1 diesel sets, paralleled, 48 h of fuel at full load

  5. LV switchboards A and B

    Form 4 switchboards with automatic transfer

  6. UPS A and B

    2N static UPS on lithium-ion batteries

  7. PDUs and busway

    Power distribution units and overhead tap-off busway

  8. The rack

    A and B rack PDUs, metered to the outlet

Cooling path: four megawatts of heat rejected at a 50 °C ambient

  1. Chillers

    N+1 air-cooled chillers rated at 50 °C

  2. Pumps and buffer tank

    Duty and standby pumps, five minutes of ride-through

  3. Chilled-water loop

    Looped distribution with sectional isolation

  4. Computer-room air handlers

    N+1 CRAH units, 24 °C supply within ASHRAE A1

  5. Hot-aisle containment

    Contained hot aisles with return to the CRAH

  6. Ready for liquid

    Coolant distribution unit provisions for rear-door and direct-to-chip cooling

Rooftop chiller plant and chilled-water headers
Rooftop chiller plant and chilled-water headers
Insulated duct and pipe runs
Insulated duct and pipe runs
The control room of a hyperbaric facility
The control room of a hyperbaric facility

Plant rooms on our own projects: the same chillers, pipework, and controls, at hospital and infrastructure scale.

Proven before handover

Five levels of commissioning, ending with the grid pulled.

  1. L1

    Factory witness

    Switchgear, UPS, generators, and chillers tested at the factory before they ship.

  2. L2

    Site inspection

    Every item checked on arrival and after installation against the drawings.

  3. L3

    Start-up

    Each system energised and run by its manufacturer, alone.

  4. L4

    Functional performance

    Each system proven against its specification: transfers, restarts, alarms, set points.

  5. L5

    Integrated systems test

    The whole facility at full load on load banks. The grid is pulled and the generators, UPS, and chillers carry the hall.

Standards and certifications

Built to the standards the industry audits against.

  • Uptime Tier III

    Concurrently maintainable power and cooling

    Uptime Institute

  • TIA-942

    The whole facility, designed to Rated-3

    TIA

  • EN 50600

    Availability classes and energy KPIs

    CENELEC, as ISO/IEC 22237

  • ASHRAE TC 9.9

    A1 envelope, 24 °C supply air

    ASHRAE

  • NFPA 75 and 76

    Detection and suppression in the hall

    NFPA

  • ISO 9001, 14001, 45001

    One integrated system on every site

    ISO

  • SBC 801

    The Saudi fire code, Civil Defense ready

    Saudi Building Code National Committee

  • CST

    Registration dossier in the handover

    Communications, Space and Technology Commission

CDCMP

Certified Data Centre Management Professional

EPI

On the team

A facility handed over by people trained to run one.

Running a data centre: operations, risk, and service levels. Held on our operations and handover team.

  • Operations

    Maintenance windows, change control, and the procedures the hall is run by.

  • Risk

    Failure scenarios worked through before handover, not after the first incident.

  • Service levels

    Availability and response targets set, measured, and reported.

Reference design

A 4 MW data centre, built in seven layers

Eastern Province, Saudi Arabia. Tier III, concurrently maintainable. 50 °C design ambient.

IT load
4,000 kW
Design PUE
1.45
Racks, 16 rows
400
Average per rack
~10 kW
Two data halls
2 × 900 m²
Building footprint
3,900 m²
Plot
11,700 m²
Tier III availability
99.982 %

The reference design is a design basis. Equipment counts, ratings, and redundancy are set per project against the site’s load study, the utility’s connection offer, and the client’s tier target.

Choosing a tier

Tier III means any chiller, UPS, switchboard or pump can be taken out of service for maintenance with the hall at full load. Tier II has spare plant on a single path; Tier IV survives a fault as well as maintenance. The reference design is Tier III, at 99.982 % design availability.

  • Tier II

    One path, with spare plant on it

  • Tier IIIReference design

    A second path, so anything can be maintained at full load

  • Tier IV

    Two live paths, so a fault changes nothing

Questions clients ask

What PUE is realistic in Saudi Arabia?

Around 1.4 to 1.5 for a Tier III hall with air-cooled chillers, because free cooling is unavailable for most of the year. Warmer supply air within the ASHRAE envelope, hot-aisle containment, and chillers selected at the real ambient are what get it there.

Can the facility take high-density or liquid-cooled racks later?

Yes, if it is designed for it now. The chilled-water loop, the plant capacity, and the floor are provisioned for coolant distribution units, so rear-door or direct-to-chip cooling can be added row by row.

How long will it run without the grid?

As long as the fuel lasts. The reference design carries forty-eight hours at full load, with a fill point at the gate and a refuelling contract in the operating plan.

Who certifies the facility?

Uptime Institute certifies the design and the constructed facility against the Tier standard; we prepare the submissions and host the demonstrations. The Kingdom's CST registration and the Civil Defense sign-off are part of the same handover.

How long does a 4 MW facility take?

From a fixed brief, roughly fifteen to eighteen months to integrated systems test, with the long-lead switchgear, transformers, generators, UPS, and chillers ordered in the first eight weeks.

Start a conversation

Bring the IT load, the site, and the tier you need.

We come back with a sized plant list, a plot layout, and a programme.