Data centre infrastructure: power, cooling, fire and controls.
We deliver the data centre infrastructure below the server: MV/LV distribution, UPS and generators, chilled-water and CRAH cooling, clean-agent fire suppression, BMS, EPMS and DCIM integration, and integrated systems testing.

The build, on scroll
Seven layers, in the order they go up.

Layer01 / 07
Site and civil
- What it is
- A plot shaped for heavy plant, heat, and dust.
- What we supply
- Plant pads, duct banks, drainage, earthing, and the fenced yard.
- The standard it meets
- TIA-942 site requirements, Rated-3
Layer02 / 07
Structure and envelope
- What it is
- A steel frame and an insulated shell, with a hall inside it.
- What we supply
- The portal frame, insulated shell, and two-hour rated partitions.
- The standard it meets
- SBC 801 compartmentation, two-hour rated
Layer03 / 07
Electrical
- What it is
- Two paths from the grid to every rack, with the engine behind both.
- What we supply
- MV intake, transformers, LV boards, UPS, generators, and busway.
- The standard it meets
- Uptime Tier III, EN 50600 power classes
Layer04 / 07
Cooling
- What it is
- Rejecting four megawatts of heat into a fifty-degree afternoon.
- What we supply
- Chiller plant, pumps, buffer tank, CRAH units, and containment.
- The standard it meets
- ASHRAE TC 9.9, A1 envelope
Layer05 / 07
Fire, safety and security
- What it is
- Detection measured in seconds, suppression that leaves no residue.
- What we supply
- Detection, clean-agent suppression, access control, and CCTV.
- The standard it meets
- NFPA 75 and 2001, SBC 801
Layer06 / 07
IT fit-out
- What it is
- Four hundred racks, sixteen rows, every one fed twice.
- What we supply
- Containment, cable tray, fibre routes, and the meet-me room.
- The standard it meets
- TIA-942 and BICSI 002
Layer07 / 07
Controls and commissioning
- What it is
- Everything measured, everything tested, then handed over.
- What we supply
- BMS, EPMS, and DCIM, and the integrated systems test.
- The standard it meets
- Uptime Tier III Certification support
Everything below the server is ours.
Our scope is everything below the server: the two paths from the grid to every rack, the plant that rejects megawatts of heat into a Gulf summer, the clean-agent fire system, the controls that watch all of it, and the commissioning that proves it. The compute, storage, and network inside the racks belong to the operator; the facility they depend on is ours.
- Green Square: power, cooling, fire, controls and structure
- The operator: compute, storage and network

Two chains carry the load: power in, heat out.
Power path: two paths from the grid to every rack
- 01
Utility intake
Dual 13.8 kV intakes from the Saudi Electricity Company
- 02
MV switchgear
Metal-clad switchgear, two sections and a bus tie
- 03
Transformers
N+1 cast-resin units, derated for 50 °C
- 04
Generators
N+1 diesel sets, paralleled, 48 h of fuel at full load
- 05
LV switchboards A and B
Form 4 switchboards with automatic transfer
- 06
UPS A and B
2N static UPS on lithium-ion batteries
- 07
PDUs and busway
Power distribution units and overhead tap-off busway
- 08
The rack
A and B rack PDUs, metered to the outlet
Cooling path: four megawatts of heat rejected at a 50 °C ambient
- 01
Chillers
N+1 air-cooled chillers rated at 50 °C
- 02
Pumps and buffer tank
Duty and standby pumps, five minutes of ride-through
- 03
Chilled-water loop
Looped distribution with sectional isolation
- 04
Computer-room air handlers
N+1 CRAH units, 24 °C supply within ASHRAE A1
- 05
Hot-aisle containment
Contained hot aisles with return to the CRAH
- 06
Ready for liquid
Coolant distribution unit provisions for rear-door and direct-to-chip cooling



Plant rooms on our own projects: the same chillers, pipework, and controls, at hospital and infrastructure scale.
Five levels of commissioning, ending with the grid pulled.
L1
Factory witness
Switchgear, UPS, generators, and chillers tested at the factory before they ship.
L2
Site inspection
Every item checked on arrival and after installation against the drawings.
L3
Start-up
Each system energised and run by its manufacturer, alone.
L4
Functional performance
Each system proven against its specification: transfers, restarts, alarms, set points.
L5
Integrated systems test
The whole facility at full load on load banks. The grid is pulled and the generators, UPS, and chillers carry the hall.
Built to the standards the industry audits against.
Uptime Tier III
Concurrently maintainable power and cooling
Uptime Institute
TIA-942
The whole facility, designed to Rated-3
TIA
EN 50600
Availability classes and energy KPIs
CENELEC, as ISO/IEC 22237
ASHRAE TC 9.9
A1 envelope, 24 °C supply air
ASHRAE
NFPA 75 and 76
Detection and suppression in the hall
NFPA
ISO 9001, 14001, 45001
One integrated system on every site
ISO
SBC 801
The Saudi fire code, Civil Defense ready
Saudi Building Code National Committee
CST
Registration dossier in the handover
Communications, Space and Technology Commission
CDCMP
Certified Data Centre Management Professional
EPI
On the team
A facility handed over by people trained to run one.
Running a data centre: operations, risk, and service levels. Held on our operations and handover team.
Operations
Maintenance windows, change control, and the procedures the hall is run by.
Risk
Failure scenarios worked through before handover, not after the first incident.
Service levels
Availability and response targets set, measured, and reported.
A 4 MW data centre, built in seven layers
Eastern Province, Saudi Arabia. Tier III, concurrently maintainable. 50 °C design ambient.
- IT load
- 4,000 kW
- Design PUE
- 1.45
- Racks, 16 rows
- 400
- Average per rack
- ~10 kW
- Two data halls
- 2 × 900 m²
- Building footprint
- 3,900 m²
- Plot
- 11,700 m²
- Tier III availability
- 99.982 %
The reference design is a design basis. Equipment counts, ratings, and redundancy are set per project against the site’s load study, the utility’s connection offer, and the client’s tier target.
Choosing a tier
Tier III means any chiller, UPS, switchboard or pump can be taken out of service for maintenance with the hall at full load. Tier II has spare plant on a single path; Tier IV survives a fault as well as maintenance. The reference design is Tier III, at 99.982 % design availability.
Tier II
One path, with spare plant on it
Tier IIIReference design
A second path, so anything can be maintained at full load
Tier IV
Two live paths, so a fault changes nothing
Questions clients ask
What PUE is realistic in Saudi Arabia?
Around 1.4 to 1.5 for a Tier III hall with air-cooled chillers, because free cooling is unavailable for most of the year. Warmer supply air within the ASHRAE envelope, hot-aisle containment, and chillers selected at the real ambient are what get it there.
Can the facility take high-density or liquid-cooled racks later?
Yes, if it is designed for it now. The chilled-water loop, the plant capacity, and the floor are provisioned for coolant distribution units, so rear-door or direct-to-chip cooling can be added row by row.
How long will it run without the grid?
As long as the fuel lasts. The reference design carries forty-eight hours at full load, with a fill point at the gate and a refuelling contract in the operating plan.
Who certifies the facility?
Uptime Institute certifies the design and the constructed facility against the Tier standard; we prepare the submissions and host the demonstrations. The Kingdom's CST registration and the Civil Defense sign-off are part of the same handover.
How long does a 4 MW facility take?
From a fixed brief, roughly fifteen to eighteen months to integrated systems test, with the long-lead switchgear, transformers, generators, UPS, and chillers ordered in the first eight weeks.
Bring the IT load, the site, and the tier you need.
We come back with a sized plant list, a plot layout, and a programme.